Energy Efficiency Tax Credits & Incentives Pay Back In Big Ways With Premier SIPS
New construction energy efficient tax incentives (IRA Tax Credits or Deductions) are simplified with high performing Premier..
Originally published in Modern Contractor Solutions
“Boss, the framing sub just called and he can’t field a crew for another week or two.” “In that case, we better tell the insulation and electrical guys we’re going to have to push them back.”
As a contractor, how many of your days start off with a conversation like that? Because traditional construction methods are a relentless string of dependent tasks, a hiccup in any stage of a project can cause a chain reaction of delays.
One powerful way to avoid such hassles is to take a systems approach to the building envelope. In other words, to use building materials that accomplish multiple tasks with one product.
With this concept in mind, more contractors are using structural insulated panels (SIPs) instead of stick framing, CMUs, and other traditional materials for commercial, institutional, and residential buildings. With one material, SIPs provide the building’s structure, insulation, and air barrier. One crew installing SIPs takes the place of multiple crews and work schedules for those three functions. Depending on the project size, the streamlined construction can mean a time savings of days, weeks, or even months.
SIPs also simplify construction in other ways, including:
Contractors for the Sarann Knight Apartments in Las Vegas installed 100,000 square feet of SIP walls in only 80 days.
One example of faster construction with SIPs—from among numerous projects throughout North America—is the Sarann Knight Apartments in Las Vegas, Nevada. In that project, the builders were able to dry-in the 82-unit complex’s four floors in only 80 days, which is substantially faster than typically required for a comparable stick-built apartment. In that time, they installed approximately 100,000 square feet of SIP walls.
“Compared to stick framing, SIP walls go up much faster since they can be installed in large sections and eliminate the need for separate on-site framing and insulation work,” says Sharon Bullock, project manager for Community Development Programs Center of Nevada (CDPCN). “The finished walls are also beautifully straight, which saves time on drywall installation, painting, and other finishing work.”
Across the city, contractors for the Clark County School District’s 900-student Jacob E. Manch Elementary School reduced the framing schedule from the 17 weeks allocated by the school district to only 7 weeks by using SIPs instead of CMUs (a 60 percent time savings). “Not only did the SIPs install faster, saving on structural building time, they reduced labor time for the electrical work,” says Gary Radzat, president of Shell Building Systems. “The panels have electrical chases built inside them so electricians don’t have to drill or modify faming. Instead, they can easily pull wires through the chases. The general contractor was shocked at how fast the panels installed—he said he’d never seen that size of schedule reduction.”
For contractors who haven’t built with SIPs before, following is a brief overview of some of the ins and outs of using the panels.
SIPs arrive at the jobsite pre-cut and labeled, ready for installation according to the building plans. “With the pre-built panels, you just have to piece the building together like a puzzle,” says contractor Glen Kamerman, partner with Kamerman Construction. The panels are compatible with nearly any type of building system, including poured concrete or block foundations. Manufacturers size SIPs to fit with standard lumber dimensions, which enables them to be easily integrated with interior walls constructed of stick framing, or with floor systems using wood I-joists. Contractors can use SIPs for roofs, or add conventional roof trusses on top of SIP walls. Crews fasten SIPs together with nails, screws, or staples, using standard power tools. Because SIPs are pre-sized, cutting is typically not necessary, although the panels can be field trimmed if necessary to fit other building systems. A primary difference between SIP construction and stick-built framing is the need to manage staging of the panels on the jobsite to avoid moving materials multiple times. Smaller panels can be set by hand, but large panels require equipment to unload and place. In most applications, SIPs are structurally self-sufficient. Where point loads from a beam or header require additional support, contractors can install additional splines at in-plane panel connections. Building designs can also use SIPs as curtain walls over steel or timber frames, which is common for large interior spaces, such as gymnasiums.
Want to learn more? Contact us, we’ll have your local SIPS consultant respond shortly!
New construction energy efficient tax incentives (IRA Tax Credits or Deductions) are simplified with high performing Premier..
The vast majority of builders in the U.S. now face demanding energy codes. Learn more about those energy codes on our blog..
Does it cost more to build green? Only in the short term! Read our blog to discover the cost benefits of building green..
As the oldest manufacturer in the SIPs industry, Premier’s SIP system is the proven prefabricated building envelope framing system for your next commercial or residential structure. Faster, stronger, and greener than outdated lumber framing methods, SIPs are the future of framing. Join the other thousands of structures built with SIPs, and contact the expert in your local region to get started.